This is a very loose timeline as to what’s happening with the repairs, since weather comes into play.

As of now, they have found, there is flashing, however, there is also tape somehow involved in the construction. The tape on there now is “NOT TO CODE”. It is not sticking. This tape is being replaced with “to code” criteria.

As far as I know now, all units on the Lian side of the bldg. will have new tape. Today, they worked on Mike Sleep’s unit and Judy’s unit. Since it’s going to rain tomorrow, they will be working on the inside of those 3 units–Judy’s, Mike’s and Irene’s.

Then they will tackle the middle 3 units and then progress on to the last 3 units. Can’t tell you the exact date–we didn’t know until yesterday that they were going to be here today for sure.

This timeline is not in stone.

Hope this isn’t too confusing, please ask if you have questions. Also, please remember to print off this email for those that don’t have internet.

thanx a bunch
Viv Nelson
vjnelson@rogers.com

Roof Et Al.

TO OWNERS 160 & 170

The roof on 160 has been repaired by Legace. It took about 1 hr.

The guy that did the work mentioned that he has not seen as bad a roof as ours. He took pics and will pass on to Andrew.

It has been suggested that Mr. Clark be approached to oversee the work done on 160. Don and Albert have already been talking and Mr. Clark is willing to oversee the work along with Don.

Think that’s all of now folks, any questions please email anyone on the board and hopefully we can help.